Power pole and line removal
The final stage of our $22.6 million, five-year electricity investment programme in Palmerston North has been completed.
The work involved the removal of about 3km of power lines and 50 poles between the Keith St and Main St substations – along parts of Keith St, SH3 and Main St.
The overhead power line was constructed in September 2016 to temporarily secure the electricity supply to Palmerston North’s CBD, following the failure of one of the three underground cables supplying the Main Street substation.
Since 2018, Powerco has been working on a series of major electricity upgrade projects for the Palmerston North community to expand, renew and rebalance its assets to ensure customers continue to have a secure electricity supply now and in the future. The most recent upgrade took place between June and August when larger capacity underground electricity cables were installed between our Ferguson and Main Street substations.
To allow the overhead line removal to be carried out safely, traffic management was requiredat times along parts of Keith St, SH3 and Main Street from mid-November. No power outages were planned for the work.
Read the media release here.
-
Project update
Friday, September 30, 2022 Installation of larger capacity cables between Ferguson and Main Street substations.View moreProject updateLinton purpose-built indoor switchroom
Wednesday, June 01, 2022 The $5 million upgrade of the Linton substation is complete.View moreProject updateSecond transformer installed at Ferguson St substation
Tuesday, March 02, 2021 A second transformer has been installed at the Ferguson St substation in Palmerston North to provide extra capacity for the city's CBD.View moreProject updateTransforming Ferguson St substation
Tuesday, March 02, 2021 Work is progressing at the Ferguson Street substation in Palmerston North with the installation of a second transformer.View more