Distributed Generation

If you are wishing to install a Distributed Generation system, e.g. solar panels, you will need to get in contact with an installer and have them apply on your behalf. 

What happens after the installer has applied?

We will assess the impact your generation will have on our network. If the load you wish to generate exceeds what is supported by the transformer at your gate, adjustments may need to be made to your application. In this case, we will notify your installer.

If there are no issues, we will advise you your application has been accepted. Once approved, your installer can install and test your system. It is important to note that your application will not be approved if the inverter does not comply with the legal requirements under AS/NZS 4777.2:2020. A list of approved inverters can be found here.

Once the installation is complete, we will require a copy of the Certificate of Compliance and Commissioning Declaration to verify the system complies with the Electricity (Safety) Regulations 2010.

Extra Note: The Electricity Industry Participation Code requires all generation installations to have metering which separately records imported and exported energy. Discuss this with your contractor and if metering upgrade is required, please contact your energy retailer.

Once submitted, how long until I am notified of the application outcome?

  • Within 10 working days if submitted under Part 1 of the Electricity Industry Participation Code;
  • Within 2 working days if under Part 1A.

Discuss with your installer which section is applicable to your application or refer to the link below for more information:

Electricity Industry Participation Code Part 6

Is there an application fee?

  • For distributed generation systems up to 10kW total capacity:No application fee (most systems installed at residential properties will likely be below 10kW).
  • For distributed generation systems above 10kW total capacity:These larger systems require a more detailed technical investigation into their effect on the network and are therefore subject to the regulated application fees detailed here.

Why do I need to apply with Powerco to install my system?

Powerco must know the location and capacity of all connected generation to be able to ensure the safety of staff, contractors and the public.

Network Export Constraints:

The following localities are approaching the maximum network capacity and are therefore subject to export capacity constraints (this may influence the amount of electricity your individual system is able to export):

Transformer Name:

Location of Transformer:

Transformer TC2-267

2193 S.H. 2, Apata

Transformer X1512

107 Veale Rd, New Plymouth

Transformer TC5456

92 Comers Rd, Whitianga

Transformer TF3-004

1303 Omanawa Rd, Tauranga

Transformer TE3-145

55 Williams Rd Nth, Tauranga

Transformer X2486

327 Bushy Park Rd, Whanganui

Transformer T9/373

Ngarata Rd, Alfredton

Transformer TE3-145

Williams Rd, Pyes Pa

Transformer Y3199   

116 Croydon Rd, Midhirst

 

We do not expect any other locations to be constrained within the next 12 months

Want to know more? View more information about:

If you have any queries about distributed generation, please email DistributedGeneration@powerco.co.nz

The connection of distributed generation is regulated by the Electricity Authority via the Electricity Industry Participation Code Part 6

Please see below for Powerco's three standard documents which are based off the code, designed to help people wishing to connect distributed generation to the Powerco Network. 

173S003 - Powerco Distributed Generation Policy

393S089 - Distributed Generation Up to 10kW Connection Standard - Generate

393S012 - Distributed Generation Over 10kW Connection Standard - Generate

Application Form for Installers: